Findings
The monitoring team sharing notes |
The Kiyagara HCII Maternity ward that will cost shs. 192Million |
•Contractor: YANKA Enterprises limited
•Work started on 22/03/2013
•Main
building at shs.192,185,200
•Placenta
PIT shs.2,000,000
•Medical
Pit shs.2,000,000
•3
stance latrine shs.9,000,000
•Total cost is shs.201,185,200
Kiyagara receives 600,410 per quarter
servicing 1000 patients from 7 Parishes per month
Unfinished works at Kiyagara HCII
•Grinding
the flour
•Painting
•Internal
door shatters
•Electrical Installations for solar and Hydro
•Plumbing
and Drainage
•Medical
waste pit
Kanara HCII
Kanara HCII, that will cost the tax payer shs. 203 million |
•Contractor: Block Technical services
•Work started on 22/03/2013
•Preliminaries at shs.27,500,000/=
•Maternity
Ward shs.
203,020,200/=
•3
stance latrine shs.
17,618,330/=
•Medical
Waste and Placenta Pit 2 x 7,000,000= Shs. 14,000,000/
Total
shs.262,138,330Actual
in the Agreement is shs.
263,138,
530/=
Is there value for money by spending shs.201,185,200 on Kiyagara and
shs.263,138, 530/= on Kanara for the same
work?
Did
the service user follow the ministry of
health specification on maternity ward construction?
Will
the maternity ward serve high population
What
is the implication of paying a 3 stance latrine at shs. 9,000,000/= in Kiyagara and shs.17,618,330/= at Kanara?
A pit latrine that will cost the tax payer shs. 14M |
What
about Placenta PIT 2,000,000 in Kiyagara and 7,000,000 at Kanara?
Getting instant feedback from the community during the joint monitoring exercise at Kiyagara HCII, Kahungye S/C, |
Compiled by
Geofrey Bwambale and Angella Biira
KALI Staff